Implementation Timeline
The Florida PALM implementation timeline has extended to July 2026.
Launching In
What Changes For Agencies:
- The go-live date for the Financials Wave, Payroll Wave, and Data Warehouse Implementation is moving from January 2026 to July 2026.
- Interface Testing will begin in August 2025 and is extending by a month.
- User Acceptance Testing will start in August 2025 and continue through May 2026 (an additional two months).
- Readiness Workplan tasks will be updated to align with the new timeline.
- Mock Conversions activities will be moving.
What Stays The Same For Agencies:
- Need for support from across the agency.
- Financials Wave, Payroll Wave, and Data Warehouse Implementation going live together.
- Designs of the Florida PALM system.
- Pace for completing agency business system build and remediation, Readiness tasks, and agency preparation for transition.
- Criticality of data cleansing, conversion preparation, and configuration review.
- Work to understand the impacts of Florida PALM to your agency business processes.
- End-to-End interface testing occurring concurrently with UAT.
- Responsibility for training on agency-specific processes.