CFO Jimmy's Patronis' Seal

Agency Readiness Reporting


Agencies must ready their people, processes, technology and data for a successful transition to Florida PALM. Agency readiness progress is reported to the Project through readiness workplan tasks and bimonthly status reports and then summarized on the Agency Status Report Dashboard. The Understanding Your Dashboard document provides an overview of all the Dashboard elements.

Beginning in March 2025, Agencies will provide quarterly Readiness Certification Updates with a final submission of Readiness Certification in November 2025.

Summary of Dashboards

The table below is a real-time, live snapshot of the current readiness dashboard dials for each agency. The status indicators will continually update.

Green indicates the measure is in a positive range, yellow represents the gaps in expected results present an increasing risk to the agency, and red indicates there are significant gaps in expected results that present an elevated risk level for the agency. The columns reflect the four dials on the Agency Status Report Dashboard.

  • CCN Composition reflects the completeness of the agency’s CCN makeup.
  • RW Task Completeness reflects the completeness of the agency’s submission of RW tasks, starting with RW Task 512.
  • RW Task Timeliness reflects the timeliness of the agency’s submission of all RW tasks to date.
  • Project-led Meeting Participation reflects the agency’s attendance at Project-led meetings during the current reporting period.

Past Due RW Tasks

The reports below are a real-time, live snapshot of the current past due RW tasks, organized by agency and by RW Task ID. RW Task Submission status is reported and maintained by the agencies in their RW Task Tracker. The Readiness Workplan and Task Tracker Job Aid describes how the RW Task Tracker is maintained. 

Agency Bimonthly Status Reports

Agency Readiness Certification

Agencies must certify that they have completed readiness activities across the four critical operational elements: people, processes, technology, and data.  Agency completed and submitted Readiness Certification will be provided to the Executive Steering Committee for review to consider each agency’s readiness as they prepare to vote on Stage Gate 4: Agency Readiness in November 2025.

The readiness activities for Agency Readiness Certification are:

  • Update 1: RW 593: Update Agency Readiness Certification – March 3 - 14, 2025
  • Update 2: RW 606: Update Agency Readiness Certification – June 2 - 13, 2025
  • Update 3: RW 619: Update Agency Readiness Certification – September 2 - 26, 2025
  • Final: RW 628: Submit Agency Readiness Certification – October 27 - November 7, 2025

 

The below provides the readiness criteria, by critical operational element, for each Update and the Final Certification along with the applicable Readiness Workplan Tasks. Click here to download a printable version.

 


Mitigating Readiness Gaps

The achievement of agency readiness is strictly to the benefit of the agency and its stakeholders. Achieving readiness certification criteria benefits the agency by having all critical operational components ready for a smooth transition upon go-live. Florida PALM can and will go-live even if some agencies have not achieved all readiness certification criteria or have gaps in their completion of readiness activities. Any agencies that have not achieved the readiness criteria at any of the certification updates or final submission (RW Tasks 593, 606, 619, and 628) must document a mitigation plan to achieve readiness or resolve the gap.

Agency mitigation plans must include at a minimum:

  • Acknowledgement of the criteria that has not been achieved.
  • Risks or issues impacting achievement of the criteria.
  • Key activities to be completed to achieve readiness and the related timeline for achieving.
  • Roles and responsibilities for the mitigation activity(ies).
  • Alternate plan to sustain agency business needs at go-live if readiness is not achieved before go-live (e.g., using spreadsheet uploads or manual entry until Agency Business System remediation is complete or limiting end user access to only those who have completed end user training and practiced job functions in the UAT (before go-live) or Sandbox (after go-live) environment).
Mitigation plans must be provided to the Project as part of the RW task(s) to update and submit readiness certification (RW Tasks 593, 606, 619, and 628) and will be shared with the ESC, as appropriate, to inform the vote on Stage Gate 4. Agencies will be required to provide regular updates to their mitigation plans until all readiness criteria are met, which may be post go-live.